Mini-competition (FKU) under Swedish public framework agreements

Practical guide to a renewed competition under a Swedish public procurement framework agreement, including invitations, evaluation and award records.
Published Mallbutiken.se
Mini-competition (FKU) under Swedish public framework agreements

A renewed competition (förnyad konkurrensutsättning, FKU) invites suppliers who are already parties to a public framework agreement to submit bids for a particular call-off. It is not an entirely new procurement. The selection method, supplier pool and award criteria must be supported by the original framework and procurement documents.

Which call-off method applies?

This guide is for Swedish contracting authorities, procurement officers and contract managers using the Swedish Public Procurement Act (LOU). It primarily describes multi-supplier frameworks governed by the directive-based rules. Below-threshold procurement, LUF and other regimes may differ. An ordinary private-sector framework agreement is not automatically an FKU under LOU.

SituationAction
Single-supplier frameworkFollow the agreed terms; do not invent competition with outsiders.
Multi-supplier framework with all terms fixedApply the specified ranking or allocation method.
Multi-supplier framework providing for FKUInvite framework suppliers capable of performing the contract in accordance with the terms.
Combined frameworkCheck the objective rules specifying when direct call-off or FKU applies.

Six steps from framework to contract

  1. Review the framework and original procurement documents: eligible users, period, ceiling, call-off method, requirements and award criteria.
  2. Identify the framework suppliers capable of performing the contract. Consult them in writing and record any reason for excluding a supplier from that pool.
  3. Send a written call-off request describing the scope, permissible clarifications, bid format, sufficient response period and framework-based evaluation method.
  4. Record invitations, questions, replies, bid receipt and opening. Do not open the bids before the deadline.
  5. Assess compliance and evaluate only under criteria permitted by the framework. Keep your reasoning and do not invent new unsupported weights.
  6. Record and communicate the award decision. Consider whether a voluntary standstill period is appropriate and retain the contract file.

Two examples

A municipality uses an IT framework with four suppliers. Where the framework provides for FKU and price and delivery criteria, it can set out a specific task and assess bids on those grounds. By contrast, where a framework requires a binding ranking for the relevant call-off, the buyer cannot switch to FKU merely to seek a lower price. Always check the full framework documents.

Evidence to retain

Keep the framework version and relevant clause, supplier list, invitation dates, communications, bid log, compliance checks, evaluations, award rationale and contract. A spreadsheet may organise evidence but cannot establish legal compliance.

Common errors and limitations

Do not confuse FKU with direct award procurement or a dynamic purchasing system. Do not improvise award criteria, open bids early or assume that a mandatory standstill automatically applies. Challenges, confidentiality and framework ceiling issues may need specialist advice.

Frequently asked questions

Can an authority always choose FKU?

No. The call-off method must follow the framework. Combined frameworks need objective rules governing the choice.

Can the buyer request a new price?

Only if supported by the framework. Substantial deviations or wholly new requirements are not freely permitted.

Is an award notice needed?

For directive-based LOU call-offs awarded after FKU, notification rules apply. A voluntary standstill may be available.

A separate guide explains commercial framework agreements and call-offs between private businesses. Related guide

Primary sources and scope

Sources reviewed on 21 November 2026. General information on Swedish law, not advice on a specific procurement.