Construction Diary 2026 – what should be documented in a site diary?
Short answer: A construction diary is used for the ongoing documentation of matters that may be significant for the contract. This can include work performed, workforce, weather, deliveries, obstacles, deviations, variations (ÄTA), and instructions. When AB 04 has been agreed upon, there is an explicit requirement for a diary, making organized daily documentation particularly important.
What should a daily construction diary contain?
| Area | Examples |
|---|---|
| Work | Tasks started, in progress, and completed |
| Resources | In-house staff, subcontractors, and machinery |
| Weather | Conditions that have affected or could affect the work |
| Deliveries | Major material deliveries, delays, and defects |
| Obstacles | What hindered work, when it started, and the impact it had |
| Variations (ÄTA) | Instruction, notification, scope, and linked variation number |
| Deviations | Quality defects, errors, corrective actions, and person responsible |
Why keep a construction diary according to AB 04?
Svensk Byggtjänst's description of a construction site diary states that AB 04 assumes the contractor will keep a diary of circumstances of importance to the contract and continuously provide the client with the content. The exact application depends on the agreement that the parties have actually entered into.
How to improve the evidentiary value
- Record on the same day, not several weeks later.
- Use fixed fields and clear date/responsibility tracking.
- Describe facts before conclusions: what happened, when, and what was the effect?
- Link photos, minutes, and emails to the correct date or event.
- Reference variation (ÄTA) numbers and obstacle notifications when they exist.
- Lock or version-control completed days so that retroactive changes can be tracked.
Keep inspection evidence separate: A construction diary entry stating that work was completed does not prove that a specific inspection was passed. Connect the diary to the inspection record, any non-conformity and re-inspection. Read our guide to construction self-inspection and the Swedish PBL control plan to distinguish contractor quality checks from the client's control plan.
Construction diary and variation register
The diary should not replace the variation (ÄTA) register. The diary shows the ongoing actual events, while the register gathers the commercial and contractual handling. When linked together, it becomes easier to track costs, time, and documentation.
Common mistakes
- Only writing “work according to plan”.
- Omitting obstacles or weather impacts until a dispute has already arisen.
- Documenting opinions without facts and timestamps.
- Failing to specify who provided an instruction.
- Lacking a connection between the diary, variation register, and schedule.
Frequently asked questions
Must all construction projects keep a diary?
There is no universal legal requirement for all construction projects. The obligation may follow from agreed standard terms, contracts, or the project's own requirements.
Are photos enough?
No. Photos are good evidence but become stronger when linked to a date, location, work task, and a written description.
Should the client's instructions be recorded?
Yes, instructions that may have significance for the contract should be documented and linked to the authorized sender.
See Construction Diary 2026/2027.
Related content
- Variation works (ÄTA) – form, notification, and register
- Subcontractor agreements – variations, work environment, and liability
- Templates for construction and contracting
See also our comprehensive guide to construction & contracting 2026.
Sources
- Svensk Byggtjänst – Construction diary for contracting
- Svensk Byggtjänst – the difference between AB 04 and ABT 06
The guide is general. The agreed construction contract determines the formal requirements that apply in the individual project.
Templates in this article
Explore the topic
Business guides – contracts, HR, AI & complianceSelf-inspection in construction 2026 – the difference between self-inspection and inspection plans according to the Planning and Building Act (PBL)
Guide to self-inspection in construction: control points, evidence, non-conformities, and the important difference between the contractor's self-in...
Business guides – contracts, HR, AI & complianceExtra work in construction contracts – form, notification, and register of extra work
Guide to ÄTA works in construction contracts: variations, additions, and omissions, notification, ordering, cost, impact on time, and ÄTA register.
Business guides – contracts, HR, AI & complianceSubcontractor Agreement – AB-U 07, Extra Work (ÄTA), Work Environment and Liability
Guide to construction subcontracting agreements: AB-U 07, ABT-U 07, scope, changes and additions (ÄTA), schedule, work environment, wage liability,...