Construction Diary 2026 – what should be documented in a site diary?

Guide to construction diaries in contracting: what should be documented daily regarding work, weather, workforce, obstacles, deviations, changes and additional work (ÄTA), instructions, and evidence.
Published Mallbutiken
Construction Diary 2026 – what should be documented in a site diary?

Short answer: A construction diary is used for the ongoing documentation of matters that may be significant for the contract. This can include work performed, workforce, weather, deliveries, obstacles, deviations, variations (ÄTA), and instructions. When AB 04 has been agreed upon, there is an explicit requirement for a diary, making organized daily documentation particularly important.

The construction diary acts as both a management tool and evidence. It should be factual, dated, consistent, and recorded as close to the event as possible.

What should a daily construction diary contain?

Area Examples
Work Tasks started, in progress, and completed
Resources In-house staff, subcontractors, and machinery
Weather Conditions that have affected or could affect the work
Deliveries Major material deliveries, delays, and defects
Obstacles What hindered work, when it started, and the impact it had
Variations (ÄTA) Instruction, notification, scope, and linked variation number
Deviations Quality defects, errors, corrective actions, and person responsible

Why keep a construction diary according to AB 04?

Svensk Byggtjänst's description of a construction site diary states that AB 04 assumes the contractor will keep a diary of circumstances of importance to the contract and continuously provide the client with the content. The exact application depends on the agreement that the parties have actually entered into.

How to improve the evidentiary value

  1. Record on the same day, not several weeks later.
  2. Use fixed fields and clear date/responsibility tracking.
  3. Describe facts before conclusions: what happened, when, and what was the effect?
  4. Link photos, minutes, and emails to the correct date or event.
  5. Reference variation (ÄTA) numbers and obstacle notifications when they exist.
  6. Lock or version-control completed days so that retroactive changes can be tracked.

Keep inspection evidence separate: A construction diary entry stating that work was completed does not prove that a specific inspection was passed. Connect the diary to the inspection record, any non-conformity and re-inspection. Read our guide to construction self-inspection and the Swedish PBL control plan to distinguish contractor quality checks from the client's control plan.

Construction diary and variation register

The diary should not replace the variation (ÄTA) register. The diary shows the ongoing actual events, while the register gathers the commercial and contractual handling. When linked together, it becomes easier to track costs, time, and documentation.

Common mistakes

  • Only writing “work according to plan”.
  • Omitting obstacles or weather impacts until a dispute has already arisen.
  • Documenting opinions without facts and timestamps.
  • Failing to specify who provided an instruction.
  • Lacking a connection between the diary, variation register, and schedule.

Frequently asked questions

Must all construction projects keep a diary?

There is no universal legal requirement for all construction projects. The obligation may follow from agreed standard terms, contracts, or the project's own requirements.

Are photos enough?

No. Photos are good evidence but become stronger when linked to a date, location, work task, and a written description.

Should the client's instructions be recorded?

Yes, instructions that may have significance for the contract should be documented and linked to the authorized sender.

Complete diary structure:
See Construction Diary 2026/2027.

See also our comprehensive guide to construction & contracting 2026.

Sources

The guide is general. The agreed construction contract determines the formal requirements that apply in the individual project.