Dewatering excavation water in Sweden: three permits and discharge tests
Guide to construction excavation water: separately assess groundwater pumping, environmental discharge and permission from the sewerage utility.
Short answer: Water pumped from an excavation can include rain, incoming groundwater and process water. Clear appearance does not establish that it is safe to discharge. Assess three different issues before pumping: whether groundwater abstraction requires approval under Chapter 11 of Sweden's Environmental Code, whether release to land or receiving waters is acceptable, and whether the local water utility accepts water into its network.
Three independent regulatory tracks
Groundwater abstraction
Removing groundwater can constitute a water operation subject to a permit. An exception under Chapter 11, Section 12, should be relied upon only if it is obvious that no public or private interests will be harmed by changes in water conditions. Document the assessment and discuss nearby wells, buildings and nature with the county administrative board.
Discharge to land or water
The relevant environmental authority may require investigation, treatment, sampling and limits to protect the receiving environment. Permission to pump groundwater does not independently authorise a discharge of contaminated water.
Connection to the stormwater or sewer network
Ask the local utility about application, connection point, technical acceptance and any agreement. Stockholm's utility requires a connection application for its network and an additional notification before discharge to the sanitary sewer. Local rules differ and do not replace environmental approvals.
Potential contaminants
Water can carry sediment, oil, fuel, blasting nitrogen residues, alkaline cement water or historical land contaminants such as metals and PFAS. Choose laboratory parameters based on site-specific risk. Generic soil guideline levels must not be presented as universal water-discharge limits.
Five checks for a sampling plan
- Describe the site, excavation depth, hydrogeology, nearby wells and receiving waters.
- Estimate pump flow, pumping period, volumes and rainfall or blasting influences.
- Specify untreated and treated sampling points and risk-based parameters such as turbidity/solids, pH, oil, metals or nitrogen.
- Agree on applicable local requirements with the regulator or utility before discharge; avoid invented universal thresholds.
- Keep records of flow, laboratory results, treatment, deviations, shutdowns and waste removal.
Choose the correct discharge route
| Route | What to check | Important caveat |
|---|---|---|
| Infiltration to ground | Consider soil, groundwater and potential contamination. | Own land is not an automatic exemption. |
| Stream, ditch or lake | Assess the receiving water and environmental requirements. | Clear-looking water can contain dissolved pollutants. |
| Stormwater network | Confirm the utility's approval and connection rules. | Not an unrestricted outlet. |
| Sanitary sewer | Follow the utility's specific notification and acceptance requirements. | Do not burden treatment plants without reason. |
| Off-site removal | Record volumes, transport and the approved receiver. | Option when treatment is inadequate. |
Scenario before a pump starts
An excavation for a pipeline fills with groundwater. The contractor first assesses whether groundwater abstraction could affect neighbouring wells or structures. Next they sample potential contaminants and plan treatment. Finally they secure the chosen outlet and utility approvals where applicable. An ordinary excavation or road-occupation permit does not by itself authorise discharge.
Operating log
- Record date, pump point, flow, outlet and responsible person.
- Link test results to sampling point, laboratory and applicable limit.
- Record filters, sediment disposal and treatment maintenance.
- Set shutdown rules for abnormal pH, sediment, sheen or laboratory result.
- Keep correspondence and approvals covering the actual work.
FAQ
Is groundwater pumping always permit-free for temporary excavation?
No. A permit may be required even for temporary works. The Chapter 11, Section 12 exception requires an obvious lack of harm to public and private interests.
Can clear water go into a storm drain?
Not automatically. Obtain the utility's position and check environmental impacts.
Do all excavations require PFAS testing?
No. Sampling is based on actual contamination risk.
Does permission from a utility cover groundwater pumping?
No. The groundwater operation and environmental discharge can need separate review.
Excavations also have separate worker-safety obligations. Read our guide to construction work environment plans under AFS 2023:3.
Sources and review
- Miljöbalken (1998:808), 2, 9 och 11 kap.
- Länsstyrelsen – Vattenverksamhet och grundvattenuttag
- Naturvårdsverket – Markavvattning och tillfällig grundvattenbortledning
- Stockholm Vatten och Avfall – Länshållningsvatten, lokala villkor
Reviewed against the Swedish Environmental Code, county authority and utility guidance on 21 November 2026. Site-specific requirements must be verified.